Your lead time only ends when the goods are ready to pick in your stock.
- Add up approval, supplier delivery time and goods receipt.
- Measure it on your last orders.
- Plan with the longest value and enter it in your reorder point.
Why your supplier's promised delivery time is not enough to calculate the lead time, and which days you have to add to the formula.

TL;DR
Your lead time only ends when the goods are ready to pick in your stock.
While you negotiate a new framework agreement for bolts, your supplier's sales rep tells you: "Delivery time: two days. Guaranteed." So you plan with two days. The bolts arrive at goods receipt on time, and still they are missing from your stock for two days and your colleagues are annoyed. Why is that? Let me explain.
The replenishment lead time includes:
Only when all three stages are done can you take the goods off the shelf, and that is when your lead time ends.
You add the three stages:
Assembly needs 24 boxes in these 4 days (6 × 4). If the company only calculates with the supplier's 2 days, it plans for 12 boxes and runs out of bolts two days earlier than its reorder point assumes.
Every order email carries a timestamp, and every delivery note carries a date. Together they give you both ends of each order. If you run an ERP, a WMS or another system for your purchasing, both dates are in the purchase order and in the goods receipt posting.
NETWORKDAYS(order_date, receipt_date, holidays) helps; the function counts the first and the last day, so subtract 1.In the following example, we use eight orders:
| Order | Working days from order email to shelf |
|---|---|
| 1 | 2 |
| 2 | 3 |
| 3 | 3 |
| 4 | 3 |
| 5 | 3 |
| 6 | 3 |
| 7 | 2 |
| 8 | 5 |
The sum is 24 days; divided by 8 orders, that is an average of 3.0 days and a longest value of 5 days. Your data does not contain the day for approval, so you add it: the replenishment lead time is 4.0 days on average and 6 days in the longest case.
With the longest value. The average sounds reasonable, but every delivery above the average lets the stock run dry. And stockouts are the worst case.
| You calculate with | Replenishment lead time | Consumption (6 boxes per day) | What happens |
|---|---|---|---|
| The supplier's quote | 2 days | 12 boxes | Stockout. In all 8 orders the shelf was empty before the goods arrived (shortest value: 2 days measured plus 1 day approval = 3 days). |
| Average | 4 days | 24 boxes | Enough in 7 of 8 cases. For the delivery that took 6 days, 12 boxes are missing, which is 2 days of material. |
| Longest value | 6 days | 36 boxes | Covers all 8 orders. |
The difference between average and maximum (12 boxes here) is the price of safety. Tied-up stock costs money, but an assembly line waiting for bolts costs more. That does not mean we recommend building up overstock.
With a partial delivery, the clock stops on the day the quantity you can keep working with is on the shelf.
If the first part lasts until the second is on the shelf, its receipt date is your receipt date. If it does not, the day the second part closes the gap counts.
Back to the example: of 60 ordered boxes, 30 are on the shelf after 3 working days and 30 after 7. At 6 boxes a day, the first 30 last 5 days, and the second part is on the shelf 4 days later, before the first 30 run out. The first delivery counts, so the measured value for this order is 3 days.
The values apply per supplier, and when you switch, you measure again. If you have two suppliers for the same item, plan with the values of the one you actually order from. If you switch depending on the situation, take the slower supplier's longest value: the shorter one only applies as long as the fast supplier can deliver.
With a new supplier or item, start with an estimate: the lead time the supplier quotes (ask whether it applies to in-stock items), plus your approval, plus goods receipt, plus a buffer for the longest value you have not measured yet. If you buy similar items from the same supplier, take their measured values as the estimate.
With the values from the example and a one-day buffer, you start at 5 days. The measurement later gives 6, so the buffer was too small. Therefore, record order and receipt dates from the very first order. Once there are enough orders to measure, the longest measured value replaces the estimate, buffer included.
A customer I supported as a Customer Success Manager often struggled with shortages of threaded bolts. He had a framework agreement with the supplier for a fixed quantity that the supplier kept in stock for him.
Then, by chance, several assembly carts in production ran empty at almost the same time. The shortfall could not be fully covered from his own stock.
Now he needed a fast delivery. Unfortunately, the call-off was higher than the remaining quantity the supplier held in stock for him. The supplier was blameless, and the customer had to improvise: he bought threaded rods and had them cut to length in-house.
So the replenishment lead time was only short up to the secured quantity. The customer then signed a new framework agreement with a higher volume, so that the supplier holds a larger quantity from which he tops up his small stock. For every framework agreement, check:
The supplier lead time is over once the delivery arrives at your door. The replenishment lead time ends on your shelf.
The German Gabler Wirtschaftslexikon defines lead time broadly: from placing the order until the goods are available to the recipient, including order transmission and the check at goods receipt. The procurement time adds further times there, such as the interval between two stock checks. Whether that works in practice is for you to decide.
The reorder point has to cover the consumption during the replenishment lead time. If you calculate with the longest value, the delay is already included: 6 boxes × 6 days = 36 boxes. If you only place the order below this quantity, the stock no longer lasts until delivery: a stockout.
You may only plan the delay once. Either you calculate with the average (4 days, 24 boxes) and put the 12 boxes for the delay into the safety stock. Or you calculate with the longest value (36 boxes), and the minimum stock only absorbs extra consumption. Using both buffers covers the same delay twice.
Three levers:
Especially for C-parts, software-supported procurement pays off: some systems, for example, reorder automatically when the reorder point is reached. Approval by purchasing is no longer needed, which shortens the lead time and saves purchasing working time.
Take the last 8 orders of your most important item, enter the order date and receipt date in a table, count the working days and add your approval. Enter the longest value in the reorder point calculator as the delivery time.
repleno Founder
Christoph worked as an electronics technician in industry for five years and saw how missing small parts slow down operations. Later, as a project manager at P.S. Cooperation GmbH (Böllhoff Group), he led system-supported C-parts logistics projects for mid-sized industrial and machine-building companies. Today, he is building repleno full-time, inventory management that helps small businesses detect demand early and automate reordering.
One click, and ChatGPT, Claude, Gemini or Perplexity give you their take.
Inventory management with barcode scanner via app. You book your stock with your smartphone, in seconds and without extra hardware.
See in black and white which items tie up capital. Spot slow movers, reduce overstock, free up money.